CRU approves up to 500 MW of long-duration storage. What comes next?

The Commission for Regulation of Utilities (CRU) has approved EirGrid’s plan to procure up to 500 megawatts (MW) of long-duration energy storage. The decision, published on 5 November, sets out how EirGrid will select projects that can help the electricity system manage changes in wind and solar output and make better use of renewable generation.

Why long-duration storage matters

Wind and solar output vary throughout the day, and the hours when renewable generation is highest do not always coincide with the hours when electricity demand is highest. Storage can absorb electricity when it is plentiful and release it later, when demand rises or renewable output falls. In parts of the grid where network limits would otherwise require wind or solar farms to reduce their output, well-located storage can also help reduce that lost generation, known as dispatch down.

EAI has consistently highlighted the urgent need for a dedicated mechanism to support investment in long-duration storage, including in its responses to EirGrid’s 2025 consultation. In this response, EAI identified the procurement as an important part of meeting Ireland’s 2030 targets and highlighted the role storage can play in reducing dispatch down.

What the CRU has decided

EirGrid will run a competitive process, with a qualification stage followed by a tender. Eligible projects must be able to draw electricity from the transmission network and supply it back for at least four hours in each direction. Successful projects will receive ten-year contracts. The tender will assess cost, expected impact, and connection method, including how much a project could reduce dispatch down given its physical location on the grid. The CRU has set 500 MW as the maximum volume. Before awarding contracts, EirGrid must inform the CRU which projects it proposes to select, their combined capacity, and the expected cost to consumers.

What EAI said in its consultation response

EirGrid’s 2025 consultation proposed a minimum procurement volume of 201 MW. EAI recommended procuring the full 500 MW within the proposed timetable. EAI’s concern was that the delivery schedule would leave too little time to use lessons from a smaller first round to run a second procurement before 2030. In the consultation response, EAI also questioned the costs and benefits of proposed eligibility thresholds, such as minimum storage duration and efficiency, given that some technologies excluded by those criteria could also help reduce dispatch down.

EAI supported the proposed ten-year contract term and raised concerns about how the contracts would work in practice. It called for the minimum revenue guarantee to account for operating costs and asked EirGrid to explain why it needed to set limits on when and how much contracted projects could charge or discharge. EAI also highlighted the difficulty for investors of assessing the risk that those limits could change after trading had closed.

What happens next

EirGrid will consult on the contractual arrangements, including how it will set charging and discharging limits and how those limits will work alongside the revenue guarantee and other incentives. The CRU will issue a further decision after that consultation and EirGrid’s subsequent recommendation.